Gas-Lift Optimisation

Find the lift-gas rate that makes the most oil and the rate that makes the most money. They are rarely the same number.

What it does

MINT sweeps a range of injection rates and performs a complete nodal solve at each one. Continuous gas lift is modelled in two sections:

  • below the operating valve, the tubing carries produced gas only;
  • above the operating valve, it carries produced plus injected gas.

This prevents the common shortcut of applying an elevated GOR to the tubing below the injection point.

What you provide

  • operating-valve injection depth;
  • current injection rate, if the well is already on lift;
  • minimum and maximum rates and the number of cases to evaluate;
  • optional oil price, produced-gas value, lift-gas cost, and fixed cost; and
  • injection-pressure constraints where applicable.

What MINT returns

Result Decision supported
Current point What the well is doing now
Maximum-rate point Injection required to make the most stable oil rate
Economic point Injection required to maximise profit
Rate uplift Production gain against the current case
Injection-rate change How far to move the current gas setting
Marginal efficiency Incremental oil per incremental lift gas
Full sweep Every stable and infeasible case for audit and plotting

A case with no stable operating point remains in the sweep as a gap. It is not reported as zero and does not cause the remaining cases to fail.

Applying the recommendation

The recommendation can be applied to the active well or saved as a scenario. Applying it re-solves the shared well model so System, Gradient, Sensitivity, Flow Assurance, AI Agent, and the report all use the lifted state.

When economics are incomplete, MINT can identify maximum rate but does not invent a profit optimum.