Production Integrity & Flow Assurance

Turn the solved pressure traverse into operational limits located along the wellbore.

Erosional velocity

API RP 14E screening compares the fastest relevant flowing condition with the limit calculated from the facility-selected empirical factor and mixture density. The factor is an engineering/facility decision rather than a universal constant.

If solids are present without an approved basis, MINT returns No answer instead of manufacturing a pass.

Liquid loading

Available criteria include:

  • Turner;
  • Coleman;
  • Belfroid, including inclination-aware variants; and
  • Nagoo, including inclination and hydraulic-diameter effects.

Applicability is shown with the result. The selected criterion can be evaluated along depth to locate where the flowing gas first loses the ability to carry liquid to surface.

Flow regime by depth

The traverse already determines local phase velocities, holdup, density, and flow pattern. MINT groups those results into depth bands so the engineer can see where the well changes between bubble, slug, churn, annular, or other returned regimes.

The well schematic highlights only the interval at risk. Selecting a node shows its pressure, temperature, phase velocities, mixture density, regime, criterion, and margin.

These are steady-state production screens, not a transient multiphase simulation.